Kathal sawmill – the mega project

In this film, we show the complete conversion and modernization of our sawmill in Kathal – documented over the period from May 2024 to May 2025.

|

What has been created here within a year is far more than a classic conversion:
It is the largest investment in the history of Johann Pabst Holzindustrie GmbH and a clear commitment to the site, to our employees and to the future of the regional timber industry.

The modernization was deliberately carried out on existing space – without additional soil sealing and using existing infrastructure.

The movie shows in detail:

  • Dismantling the old systems
  • Foundation and construction work
  • Assembly of the new saw line
  • Hall construction and infrastructure
  • Modern sorting and conveying technology
  • Technical milestones
  • the path from the groundbreaking ceremony to the finished plant

Factbox:

  • Period: May 2024 to May 2025
  • Investment volume: around € 40 million
  • Largest investment in the company’s history
  • state-of-the-art sawing technology
  • Long-term site security in Kathal
  • Improvement of working conditions, noise and flood protection
  • Sustainable modernization without new construction on a greenfield site